D2P CASE 163

How THEON Used Vertical Integration to Secure Critical Night-Vision Components

Facing constrained global capacity for image intensifier tubes, THEON combined long-term supply agreements, strategic component inventory, and the acquisition of Harder Digital. Bringing part of this upstream capacity under its control supported faster delivery as demand grew. Revenue increased from €218.72m in 2023 to €443.5m in 2025.
BEFORE2023 revenue €218.7m
AFTER2025 revenue €443.5m
OUTCOMESuccess
MODELElectro-optical systems sales to governments and defense companies

Full Story

Background & Opportunity

THEON sells night-vision, thermal-imaging, and electro-optical systems to governments, armed forces, and defense prime contractors. Its revenue model extends beyond individual system sales to include long-term framework contracts, localized international production, and after-sales support. In this model, winning an order is only the first step. The ability to obtain critical components on time and complete delivery determines how quickly an order can be converted into revenue. Image intensifier tubes are among the most important and expensive components in night-vision equipment. As demand to modernize night-vision capabilities increased across Europe and the United States, THEON’s market opportunity expanded. Yet limited spare capacity across the global supply base meant that component availability could also become a constraint on growth. THEON generated revenue of €218.72m in 2023, giving it a solid commercial base for its subsequent expansion. Before 2024, however, THEON purchased image intensifier tubes more frequently through ad hoc orders. That approach could support ordinary procurement requirements, but it made it harder to coordinate upstream production with THEON’s delivery schedule when demand accelerated. If critical components failed to arrive on time, the company could win more system orders while still being unable to expand output at the required pace. Delivery lead times could then lengthen even as the order book grew. Defense customers can also place unexpected orders that require rapid delivery. Reliance on ad hoc purchasing made it more difficult to align component arrival dates with these customer requirements. THEON was therefore confronting more than a conventional procurement-cost problem. It faced a structural mismatch among order growth, constrained component capacity, and its ability to deliver finished systems. The company needed to answer three related questions. First, how could it obtain multiyear capacity commitments from external suppliers? Second, how could inventory be used to prepare for orders requiring rapid delivery? Third, should THEON bring part of image intensifier tube manufacturing under group control? In February 2024, THEON’s IPO generated net proceeds of €93.9m, providing the financial foundation for acquisitions and growth investment. This capital allowed management to elevate supply security from a routine purchasing matter to a capital-allocation decision. THEON could now combine external long-term procurement with investment in upstream manufacturing. Each lever addressed a different part of the constraint. An external agreement could coordinate future production volumes and delivery schedules directly with a major supplier. Building inventory of critical components could improve readiness for unexpected large orders. Taking control of an upstream manufacturer could create partial in-house supply, although doing so would require investment in equipment upgrades and production-line expansion. THEON ultimately treated these approaches as complementary rather than mutually exclusive. The strategic objective was not to eliminate external suppliers entirely. It was to reduce the uncertainty created by depending on a single ad hoc purchasing model during a period of rapidly rising demand. Long-term external supply, inventory readiness, and partial control of production capacity together created a broader delivery safeguard. The limits of the conclusion are equally important. Rising European defense demand, a major OCCAR contract, new products, and geographic expansion also contributed to THEON’s performance. The supply chain strategy cannot be treated as the sole cause of all revenue growth. Its more precise role was to provide a critical operating condition that helped the company maintain rapid delivery and expand its business as demand increased.

Original Problem / Model

Before 2024, THEON purchased image intensifier tubes more frequently through ad hoc orders. With limited spare global capacity, a concentration of modernization demand and unexpected large orders could create shortages, lengthen delivery times, and disconnect growth in orders from the company’s ability to expand actual production.

Turning Point

In 2024, THEON made supply security a core strategy. It first secured a multiyear arrangement with Exosens, then acquired a 60% interest in Harder Digital, while using critical-component inventory to support orders requiring rapid delivery.

Core Decision

THEON decided to use IPO proceeds and its own cash for two layers of protection: reserving future capacity from an external supplier while investing in and controlling upstream manufacturing capacity.

Execution / Model / Acquisition Changes

The Exosens agreement covered 2025—2026 and included a 2027 option. On November 14, 2024, THEON acquired a 60% interest in Harder Digital for total purchase consideration of €32.308m. It also invested in equipment upgrades and expanded production lines in Germany and Latvia.

Measurable Results

Revenue increased from €218.72m in 2023 to €352.36m in 2024 and reached €443.5m in 2025. After investment, Harder Digital’s annual capacity rose from approximately 6,000 tubes to approximately 15,000 tubes. THEON absorbed approximately 66% of output, while Harder Digital also secured a €25m third-party order.

Lessons

The supply chain decision was not the sole cause of THEON’s growth. However, the case shows that when a critical component can restrict delivery, long-term agreements, appropriate inventory, and upstream control can work together as a stronger safeguard than continued reliance on ad hoc purchasing alone.

Long-term procurement, inventory, and vertical integration became critical enablers of rapid delivery and growth.

Deep Analysis

Option B addresses supply volume, delivery timing, and operational control together. Long-term agreements reserve several years of external supplier capacity, inventory supports orders requiring rapid delivery, and control of Harder Digital provides partial in-house supply. Option A would leave THEON exposed to limited capacity and ad hoc purchasing. Option C would sacrifice opportunities during a period of rising demand. Option D would not directly resolve the shortage of critical components. The performance gains cannot be attributed entirely to this supply chain decision: stronger European defense demand, the OCCAR contract, new products, and geographic expansion also contributed.

Turning Point

In 2024, THEON elevated supply security into a core strategy. It first signed an Exosens supply agreement covering 2025—2026 with a 2027 option, then acquired a 60% interest in Harder Digital. This shifted the company from ad hoc purchasing toward a combination of long-term agreements, inventory, and partially controlled production capacity.

Before vs After

Before
Before 2024, THEON relied more heavily on ad hoc orders for image intensifier tubes, creating a risk of longer delivery times when limited global spare capacity tightened.
After
Through multiyear supply agreements, critical-component inventory, and control of an upstream manufacturer, THEON gained more stable external supply and partial in-house capacity.

GoGoUp Five Powers

Discover5/5
★★★★★
Analyze4/5
★★★★☆
Execute5/5
★★★★★
Decide5/5
★★★★★
Create4/5
★★★★☆

Discover5/5

THEON identified image intensifier tubes as critical, high-cost night-vision components whose limited global capacity could prevent secured orders from being converted into on-time deliveries.

Analyze4/5

The company reframed the issue from procurement price to capacity, lead times, and supply control, distinguishing the roles of ad hoc purchasing, long-term agreements, and controlled production.

Execute5/5

THEON signed a multiyear supply agreement, built critical-component inventory in advance, acquired control of Harder Digital, and expanded production lines in Germany and Latvia.

Decide5/5

THEON used IPO proceeds and its own cash to secure external supply and invest in upstream capacity instead of continuing to rely solely on ad hoc orders.

Create4/5

The company established a model combining long-term external supply with partial in-house production, while the expanded Harder Digital business also secured a €25m third-party order.

Growth depends on more than winning orders: companies must secure the components that constrain delivery and balance inventory, contracts, and upstream control.
Evidence / Sources
THEON’s 2024 and 2025 reports, company announcements, and ASDNews support the revenue, supply agreement, acquisition, and capacity-expansion facts. GoGoUp Five Powers assessments are for educational analysis only.